APPROVAL OF REVISION TO ARCHITECT'S CONTRACT FOR THE FRUITVILLE ELEMENTARY SCHOOL-CLASSROOM WING ADDITION PROJECT

Description
Due to a mathematical calculation error, an incorrect contract total of $448,525.00 was submitted and Board approved on 7/22/2014, Item #37.  The corrected contract total is $464,650.00 which represents an increase of $16,125.00.  The construction budget is approximately $6,500,000.00.  Funds for this project are available in the capital budget account.

Recommendation
That the project be accepted as complete and the final payment to contractor be approved as presented.

Contact
LEMPE & SMITH

Financial Impact
Capital:  $16,125.00